Time and Work- Aptitude Questions and Answers

View in English View in Hindi

A is twice as good as workman as B and therefore able to finish a piece of work in 30 days less than B. In how many days can they complete the whole work together?

A)
20 days

B)
40 days

C)
60 days

D)
80 days


Correct Answer :

20 days


Explanation :

Let A takes X days to complete the work and B takes 2X days
according to question, A takes 30 days less than B, that is X = 2X – 30
X=30

thus ,A take 30 days to complete the work and B takes 60 days
hence, A and B one days work is 1/30 + 1/60 = 1/20

Therefore, the whole job together they will be completed in 20 days

16 workers working 6 hours day can build a wall of length 150m, breadth 20m, and height 12m in 25 days. In how many days 12 workers, working 8 hours a day will build a wall of length 800m, breadth 15m and height 6m?

A)
50 days

B)
25 days

C)
25 days

D)
60 days


Correct Answer :

50 days


Explanation :

to build a wall of 150*20*12=36000 ,hours required = 16*6*25=2400

to build a wall of 800*15*6=72000 , which is exactly twice as big as the first one,
You need 2400*2 hours = 4800
that is 12*8*days = 4800
days = 4800/96 = 50

A can do a piece of work in 10 days while B can do the same work in 20 days. They start together but A leaves after three days. How many days will B take to complete the remaining work?

A)
14 days

B)
8 days

C)
12 days

D)
11 days


Correct Answer :

11 days


Explanation :

One day's work of A and B = (1/10 + 1/20) = 3/20

Work done by A and B together in the 3 days = 3 (1/10 + 1/20) = 9/20
Remaining Work =1- 9/20 = 11/20

1/20 Work done by B in a day
thus,11/20 Work wll be done by B in (11/20)*20 =11 days

If 3 men or 4 women can reap a field in 30 days, how long will 3 men and 6 women take to reap it?

A)
21 days

B)
16 days

C)
18 days

D)
12 days


Correct Answer :

12 days


Explanation :

3 men can complete work in 30 days
so, Work done by one man in a day = 1/(3*30)
and Work done by one women in a day =1/(4*30))

Thus, 3 men and 6 women will work in a day => 3/(3*30) + 6/(4*30)
= 1/30( 1 + 6/4)
= (1/30)*(10/4) =>1/12

3 men and 6 women do 1/12th part of work in a day,so they will complete the work in 12 days

A is twice as good a workman as B, and finishes the work in 14 days less than B. In how many days can it be done by A alone?

A)
14

B)
21

C)
28

D)
42


Correct Answer :

14


Explanation :

let A take X days to complete the work and B takes 2X days
according to question, A takes 14 days less than B, that is X = 2X – 14 =>14

thus ,A take 14 days to complete the work and B takes 28 days.

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

A)
4

B)
5

C)
6

D)
10


Correct Answer :

6


Explanation :

let X persons required to complete the work in 20 days
then, work done => 30 * 24 = X *20

thus ,num of persons, X = 720 / 20 => 36

extra ,more people required = 36 - 30 = 6 persons

A is twice as good workman as B. Together, they finish the work in 14 days. In how many days can it be finish by B separately?

A)
21

B)
48

C)
42

D)
35


Correct Answer :

42


Explanation :

let A take X days to complete the work and B takes 2X days.
A's one day work = 1/X , B's one day work = 1/2X
(A+B)'s one day work => 1/X + 1/2X = 1/14
=> 14/X + 14/2X = 1
=> 14+7=X
=> X=21

Thus,
B working alone will require 2*21=42 days to complete the work
A working alone will require 21 days to complete the work

A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?

A)
70 days

B)
171/4 days

C)
190/7 days

D)
120/7 days


Correct Answer :

120/7 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n

Then (A + B)'s 1 day's work = (1/30 + 1/40) = 7/120
Hence, Time taken by both to finish the work = 120/7 days

A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in ?

A)
3 days

B)
5 days

C)
7 days

D)
11 days


Correct Answer :

5 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n

B's 9 day's work = 9 * (1/12) = 3/4
Remaining work = (1 - 3/4) = 1/4
1/4 work is done by A in = 20 * (1/4) = 5 day

A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it?

A)
12 days

B)
20 days

C)
24 days

D)
28 days


Correct Answer :

24 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n
If A and B, working together,and can complete a piece of work in X days. If A, working alone, can
complete the work in Y days, then B working alone, will complete the work in XY/(Y-X) days.

Then ,B alone can complete = (12 * 8) / (12 - 8) = 96/4 = 24 days

A can do a piece of work in 12 days. B is 60% more efficient than A. The number of days, it take B to do the same piece of work is ?

A)
15/2

B)
25/4

C)
8

D)
6


Correct Answer :

15/2


Explanation :

A's 1 day's work = 1/12
B's 1 day's work = 1/12 + 60% of 1/12 = 1/12 x 160/100 = 2/15

Hence,B can do the work in 15/2 days

X is 4 times more efficient than Y, in what proportion will the number of days taken by X and Y to complete any work?

A)
8 : 1

B)
1 : 5

C)
6 : 8

D)
5 : 1


Correct Answer :

1 : 5


Explanation :

If A is twice as good a workman as B, then:
(a) Ratio of work done by A and B is 2:1.
(b) Ratio of times taken by by A and B to finish a work is 1:2.

Efficiency (X : Y) = 5 : 1
No. of days (X : Y) = 1 : 5

20 persons completed 1/3 rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?

A)
20

B)
12

C)
18

D)
40


Correct Answer :

20


Explanation :

Work done by 20 persons = 1/3
Remaining work = 1- 1/3 = 2/3
So for double work in same days we need double number of people i.e. 40.

Hence, 20 more people are needed.

6 children and 2 men complete a certain piece of work in six days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?

A)
6

B)
8

C)
9

D)
15


Correct Answer :

6


Explanation :

6C + 2M = 6 days
36C + 12M = 1 day
As is given 1M = 2C
Then, 36C +12*2C = 1 day
60 children can work in 1 day
Now, 5 men = 10 children
Then, 10 children can work in 6 days.So 5 men also can complete the work in 6 days.

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days,then the time taken by 15 men and 20 boys in doing the same type of work will be?

A)
4

B)
6

C)
8

D)
9


Correct Answer :

4


Explanation :

Let a man one day work is X and a boy one day work is Y. Then
6x + 8y =1/10
26x + 48y =1/2
After resolving above equations

x =1/100
y =1/200

15x + 20y = 15/100+20/200 = 1/4
Hence, 15 men and 20 boys to do that work in 4 days

6 men or 10 women can reap a field in 15 days, then the number of days that 12 men and 5 women will take to reap the same field is :

A)
5

B)
6

C)
8

D)
12


Correct Answer :

6


Explanation :

Work done by 6 men = work done by 10 women.
Work done by 1 man = work done by 10 / 6 women= 5/3 women

∴ 12 men + 5 women = 12 x ( 5 / 3) + 5 = 25 women
∴ W1 * D1 = W2 * D2 [W = women, D=days]
10 * 15 = 25 * D2
D2 = 6

Latest Updates

Percentage

20% of a quantity is Rs 400, the quantity equals?

Time and Work

A certain piece of work can be completed by 12 men in 9 days. After they have worked for six days, six more men joined them. How many days will it take to complete the remaining work?

Ratio and Proportion

A certain sum was divided among A, B and C in the ratio 5 : 7 : 6. If B received Rs 4500 more than C, find C's share?

Problems on Ages

A is two years older than B who is twice as old as C. If the total of the ages of A, B and C be 27, the how old is A?

Time and Work

A and B can together finish a work in 30 days. They worked at it for 20 days and then B left. The remaining work was done by A alone in 20 more days. B alone can do the entire work in?

Discount

A retailer buys a washing machine marked at Rs 4800 and gets two successive discounts of 15% and 5%. If he spends Rs 124 on transportation and sells the washing machine at a gain of 13%, then find the selling price of the machine.

Boats and Streams

Speed of a boat in still water is 10 kmph, and speed of the stream is 5 Kmph. In how many minutes would the boat cover a distance of 5 km downstream?

Problems on Ages

The age of two persons differ by 2 years. If the sum of their ages is equal to the square root of 144 then find the age of the elder among the two person?

The age of A is six times the age of his son. A's father is 40 years older than him. Together, they are 118 years old. What is the age of A?

Average

The average mark of 50 students is 75. If the marks obtained by one of the student had been written as 36 instead of 86, then the corrected average of marks is:

Unix/Linux

What is inode?

Problems on Ages

A group of 15 people has average age of 45 years. Two persons are excluded and the average of the remaining is increased by 5 years. What is the average age of the two persons who have been excluded?

Average

In the world cup, Yuvraj has a batting average of 65 in 7 matches till semi-final. How much should Yuvraj score in the 8th match ie the final match to get a batting average of 85?

Problems on Trains

A train takes 8 sec to cross a 75 metre long platform at a speed of 90 km/h. What is the length of the train?

Alligation or Mixture

In what ratio must Rs 50 per kg salt be mixed with Rs 80 per kg salt to obtain a mixture worth of Rs 60 per kg?

Numbers

Find the sum of the given series: 3 + 9 + 27 + 81 + 243 + 729 + 2187 + 6561

Average

Find the average. 62, 54, 44, 36, 28 & 22

Percentage

In an examination, 36% of the students failed in English and 40% failed in Hindi. If 20% of the students failed in both subjects, then the pass percentage is?

Latest Job Notifications

Jobs in Madhya Pradesh

राष्ट्रीय स्वास्थ्य मिशन मध्य प्रदेश National Health Mission MP(NRHM) - 5215 पद - 22/06/2021 अंतिम तिथि

Jobs in Punjab

पंजाब स्टेट पावर कॉर्पोरेशन लिमिटेड Punjab State Power Corporation Limited (PSPCL) - 2632 पद - 20/06/2021 अंतिम तिथि

Jobs in Chhattisgarh

स्वास्थ्य सेवा निदेशालय, छत्तीसगढ़ Department of Health & Family Welfare, Chhattisgarh - 267 पद - 26/06/2021 अंतिम तिथि

Government Jobs

दिल्ली सबऑर्डिनेट सर्विस सिलेक्शन बोर्ड Delhi Subordinate Services Selection Board(DSSSB) - 5807 पद - 03/07/2021 अंतिम तिथि

Jobs in Madhya Pradesh

राष्ट्रीय स्वास्थ्य मिशन मध्य प्रदेश National Health Mission MP(NRHM) - 2850 पद - 31/05/2021 अंतिम तिथि

Government Jobs

इंडियन पोस्ट सर्विस Indian Post Service - 4368 पद - 29/05/2021 अंतिम तिथि

दिल्ली सबऑर्डिनेट सर्विस सिलेक्शन बोर्ड Delhi Subordinate Services Selection Board(DSSSB) - 7236 पद - 24/06/2021 अंतिम तिथि

Banking Jobs

Reserve Bank of India (RBI) - 841 Posts - 15/03/2021 Last date

Institute of Banking Personnel Selection (IBPS) - CRP SPL-IX - 1163 Posts - 26/11/2019 Last date

Government Jobs

Reserve Bank of India (RBI) - 199 Posts - 11/10/2019 Last date